BEIJING, Sept. 1 (Xinhua) -- As the International Broadcasting Center (IBC) and Main Press Center (MPC) for the Beijing Winter Olympic Games, the China National Convention Center Phase II has completed its main steel structure engineering 76 days ahead of schedule, the construction unit confirmed on Tuesday.
The construction scale of Phase II is 1.5 times of that of Phase I, with a total construction area of 780,000 square meters, but the construction period has been reduced by one year.
The underground part of the second phase was finished in November last year and the construction of the steel structure above ground was interrupted by the outbreak of this year's COVID-19 pandemic.
The construction unit was quick to adjust its construction plan and coordinate with the raw material suppliers outside Beijing in a bid to speed up the schedule when construction resumed.
The MPC and IBC will be delivered to BOCOG in July 2021.
Fire brigade in Shanghai holds group wedding
Tourists enjoy ice sculptures in Datan Town, north China
Sunset scenery of Dayan Pagoda in Xi'an
Tourists have fun at scenic spot in Nanlong Town, NW China
Harbin attracts tourists by making best use of ice in winter
In pics: FIS Alpine Ski Women's World Cup Slalom
Black-necked cranes rest at reservoir in Lhunzhub County, Lhasa
China's FAST telescope will be available to foreign scientists in April
"She power" plays indispensable role in poverty alleviation
Top 10 world news events of People's Daily in 2020
Top 10 China news events of People's Daily in 2020
Top 10 media buzzwords of 2020
Year-ender:10 major tourism stories of 2020
No interference in Venezuelan issues
Biz prepares for trade spat
Broadcasting Continent
Australia wins Chinese CEOs as US loses